LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION: grid connection queue

LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 60 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Aug 2031 to 29 Aug 2031.

1project in the queue
60 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
60 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
D&G 2Greyland Energy Park LimitedOnshore wind6029 Aug 2031High15 Jul 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.