Glennifer Road BESS 132kV substation: grid connection queue

Glennifer Road BESS 132kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Jul 2028 to 31 Jul 2028.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
150 MWholding Gate 2
1date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Glennifer Road BESSDrax BESS Neilston LimitedBattery storage15031 Jul 2028High31 Jul 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
21 Jul 2026Glennifer Road BESS30 Oct 202731 Jul 2028+9 months

Thinking of connecting near Glennifer Road BESS 132kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.