Tarland 132/33kV GSP: grid connection queue
Tarland 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 20 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2026 to 31 Oct 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tarland Battery Storage System | Tarland Limited | Battery storage | 20 | 31 Oct 2026 | n/a | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ballater Primary | SSEN Distribution | 5.7 km | 0 MW | 0 MW |
| Strathdon Primary | SSEN Distribution | 10.6 km | 0 MW | 1.9 MW |
| Aboyne Primary | SSEN Distribution | 18.1 km | 0 MW | 0 MW |
| Tarland GSP | SSEN Distribution | 19.0 km |
Thinking of connecting near Tarland 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Dorenell Extension Wind Farm 400kV: 610 MW waiting
- Dorenell BESS 132KV substation: 38 MW waiting
- Clashindarroch Windfarm Extension 132kV: 145 MW waiting
- Glendye Wind Farm: 167 MW waiting
- Bridge of Dun: 50 MW waiting