Seabank: grid connection queue
Seabank GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 135 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2038 to 31 Oct 2038.
1project in the queue
135 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Severn Road Avonmouth | FPC ELECTRIC LAND LIMITED | Mixed and other | 135 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Seabank?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- SEABANK 400/33kV SUBSTATION: 50 MW waiting
- West Country Connection Node C 400kV: 1,200 MW waiting
- West Country Connection Node E 400kV: 480 MW waiting
- West Country Connection Node A 400kV: 300 MW waiting
- Woolavington 400kV: 1,630 MW waiting