Indian Queens 400kV: grid connection queue
Indian Queens 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 580 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jul 2024 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Indian Queens | PIVOTED POWER LLP | Battery storage | 48 | 30 Jul 2024 | n/a | Consents Approved | none | |
| St Dennis Hendra | SAMBAR POWER LIMITED | Battery storage | 48 | 31 Oct 2024 | n/a | Consents Approved | none | |
| Indian Queens Energy Centre | IQ ENERGY CENTRE LIMITED | Solar + storage | 48 | 30 May 2027 | High | 29 May 2029 | Consents Approved | 2 |
| Indian Queens | GRIDMOVE LTD | Solar + storage | 437 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 11 Aug 2026 | Indian Queens Energy Centre | 31 May 2025 | 30 May 2027 | +24 months |
Thinking of connecting near Indian Queens 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.