Hutton 400kV: grid connection queue
Hutton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Nov 2037 to 1 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Eskrigg End BESS | Energi Generation 6 Ltd | Battery storage | 249 | 1 Nov 2037 | Low | 1 Nov 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 609663 | Electricity North West | 4.2 km | 4.6 MW | 0.7 MW |
| Primary substation 609659 | Electricity North West | 7.8 km | 12 MW | 2.7 MW |
| Primary substation 609656 | Electricity North West | 10.5 km | 15 MW | 0.4 MW |
| Primary substation 609054 | Electricity North West | 11.6 km | 13 MW | 0 MW |
| Primary substation 609662 | Electricity North West | 12.0 km | 3.2 MW | 0 MW |
| Bulk supply point 609657_609659 | Electricity North West | 15.8 km | 27 MW | 12 MW |
Thinking of connecting near Hutton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Spennymoor 400kV: 850 MW waiting