Amersham Main 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 125 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Vox Charlie | Vox Charlie Ltd | Battery storage | 125 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ilmer Grid 33kV | UK Power Networks | 1.6 km | 61 MW | 15 MW |
| Ilmer Primary 11kV | UK Power Networks | 2.0 km | 8.4 MW | 2.3 MW |
| Saunderton Primary 11kV | UK Power Networks | 4.8 km | 17 MW | 9.1 MW |
| Chinnor Primary 11kV | UK Power Networks | 6.1 km | 8.4 MW | 7.3 MW |
| Thame Primary 11kV | UK Power Networks | 6.5 km | 16 MW | 5 MW |
| North Dr Primary 11kV | UK Power Networks | 7.9 km | 16 MW | -3.6 MW |
Thinking of connecting near Amersham Main 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Amersham Main 400kV: 250 MW waiting
- Chiltern Connection Node C 132kV: 150 MW waiting
- Chiltern Connection Node B 400kV: 1,000 MW waiting
- Chiltern Connection Node A 400kV: 750 MW waiting
- Chiltern Connection Node C 400kV: 1,500 MW waiting