Amersham Main 132kV: grid connection queue

Amersham Main 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 125 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
125 MWwaiting to connect
99 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Vox CharlieVox Charlie LtdBattery storage12531 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Ilmer Grid 33kVUK Power Networks1.6 km61 MW15 MW
Ilmer Primary 11kVUK Power Networks2.0 km8.4 MW2.3 MW
Saunderton Primary 11kVUK Power Networks4.8 km17 MW9.1 MW
Chinnor Primary 11kVUK Power Networks6.1 km8.4 MW7.3 MW
Thame Primary 11kVUK Power Networks6.5 km16 MW5 MW
North Dr Primary 11kVUK Power Networks7.9 km16 MW-3.6 MW

Thinking of connecting near Amersham Main 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points