South Humber Connection Node A 400kV: grid connection queue
South Humber Connection Node A 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,240 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 31 Oct 2035 to 30 Oct 2039.
3projects in the queue
1,240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Killingholme Energy Park | EXAGEN GROUP LIMITED | Solar + storage | 500 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
| Lincolnshire Energy Park | WIND 2 LIMITED | Mixed and other | 500 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | none |
| Crawcroft Lane Solar and Storage | BSR APPLICATIONS LIMITED | Solar + storage | 240 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near South Humber Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Osbaldwick (North Humber Connection Node E) 132kv: 200 MW waiting
- SOUTH HUMBER CONNECTION NODE A 132kV: 240 MW waiting
- South Humber Connection Node A: 800 MW waiting
- Raventhorpe 400kV: 250 MW waiting
- North Humber Connection Node B 132kV: 200 MW waiting