Cairnford: grid connection queue
Cairnford GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
3 projects with 146 MW are waiting to connect here (largest by capacity: onshore wind, onshore wind + storage). Contracted dates run from 4 Jun 2027 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Clashindarroch 2 | VATTENFALL WIND POWER LTD | Onshore wind | 63 | 4 Jun 2027 | High | 1 Aug 2029 | Under Construction/Commissioning | 2 |
| Cairnborrow Wind Energy Hub | BPUWL 29 LIMITED | Onshore wind + storage | 43 | 31 Oct 2031 | High | 16 Sep 2033 | Scoping | 1 |
| Tarbuckle Hill Wind Farm | ENERGIEKONTOR UK LTD | Onshore wind | 40 | 31 Oct 2031 | High | 16 Sep 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cairnford GSP | SSEN Distribution | 0.4 km | ||
| Huntly Primary | SSEN Distribution | 4.1 km | 0 MW | 8.1 MW |
| Limehillocks Primary | SSEN Distribution | 10.3 km | 0 MW | 0 MW |
| Keith Primary | SSEN Distribution | 10.8 km | 0 MW | 6.4 MW |
| Keith 2 GSP | SSEN Distribution | 10.8 km | ||
| Keith 1 GSP | SSEN Distribution | 10.9 km |
Thinking of connecting near Cairnford?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New North East 275kV: 200 MW waiting
- Keith Solar Farm 275kV: 150 MW waiting
- Keith 2 132/33kV GSP: 132 MW waiting
- Keith 132kV: 48 MW waiting
- Keith 1 132/33kV GSP: 39 MW waiting