Lovedean 400kV: grid connection queue
Lovedean 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 356 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 1 Jun 2028 to 31 Mar 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lovedean Greener Grid Park | Statkraft UK Ltd | Battery storage | 50 | 1 Jun 2028 | High | 1 Jun 2030 | Scoping | 1 |
| Lovedean (Tertiary) | LOVEDEAN GREEN LIMITED | Solar + storage | 57 | 30 Oct 2029 | Medium | 30 Oct 2029 | Scoping | none |
| EcoLovedean | Econergy International Limited | Battery storage | 249 | 31 Mar 2031 | Medium | 31 Mar 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ashling Road Primary | SSEN Distribution | 3.6 km | 0 MW | 0 MW |
| Emsworth Primary | SSEN Distribution | 6.5 km | 0 MW | 0 MW |
| Market Primary | SSEN Distribution | 6.7 km | 0 MW | 0 MW |
| Hunston Primary | SSEN Distribution | 8.4 km | 0 MW | 0 MW |
| Hunston BSP | SSEN Distribution | 8.4 km | 0 MW | 0 MW |
| Leigh Park Primary | SSEN Distribution | 8.7 km | 0 MW | 0 MW |
Thinking of connecting near Lovedean 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Solent Connection Node C 400kV: 2,400 MW waiting
- Solent Connection Node A 132kV: 100 MW waiting
- Solent Connection Node B 132kV: 120 MW waiting
- Fawley 132kV: 450 MW waiting
- Marchwood 400kV: 200 MW waiting