Seat Hill 132kV: grid connection queue
Seat Hill 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 90 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Seat Hill Wind Farm | PERIGUS ENERGY UK LIMITED | Onshore wind + storage | 90 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Seat Hill Wind Farm | 31 Jul 2032 | 30 Oct 2035 | +39 months |
| 13 Oct 2026 | Seat Hill Wind Farm | 30 Oct 2035 | 31 Jul 2032 | -39 months |
Thinking of connecting near Seat Hill 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.