Gresham House Gretna 400/132kv: grid connection queue
Gresham House Gretna 400/132kv Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 456 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 30 Oct 2032.
2projects in the queue
456 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Gresham House Gretna BESS | ALBUSIA LTD | Battery storage | 400 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
| GH DEVCO Gretna Green BESS | GRETNA ENERGY STORAGE LIMITED | Battery storage | 56 | 30 Oct 2032 | Low | 30 Oct 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Gresham House Gretna 400/132kv?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.