Achrugan 132kV: grid connection queue

Achrugan 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 149 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Jul 2030 to 31 Jul 2030.

1project in the queue
149 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
149 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Achrugan Wind FarmStatkraft Windco 1 LimitedOnshore wind + storage14931 Jul 2030High16 Jun 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Achrugan 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.