Loch Fearna Pumped Storage 400/18kV: grid connection queue

Loch Fearna Pumped Storage 400/18kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 300 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 28 Oct 2032 to 28 Oct 2032.

1project in the queue
300 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Loch Fearna Pumped StorageFEARNA PSH LIMITEDHydro, pumped storage and tidal30028 Oct 2032Low28 Oct 2032Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Loch Fearna Pumped Storage 400/18kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.