Grid Delay Index
How often Great Britain's grid connection dates move, from our weekly copies of NESO's register. Updated with each new register.
Month by month
Each row counts connection dates that moved by a month or more between weekly copies of the register. 210 moved later and 77 earlier between 2 Jun 2026 and 17 Nov 2026; the typical later move was 19 months.
| Month seen | Later | Earlier | MW pushed later | Months of delay added |
|---|---|---|---|---|
| November 2026 | 25 | 6 | 8,428 MW | 548 |
| October 2026 | 99 | 62 | 33,738 MW | 2,722 |
| September 2026 | 14 | 3 | 3,110 MW | 269 |
| August 2026 | 23 | 2 | 2,792 MW | 391 |
| July 2026 | 30 | 1 | 4,875 MW | 672 |
| June 2026 | 19 | 3 | 4,243 MW | 377 |
The two-year view: near dates slip most
We compared every project waiting in our register copy of 6 Dec 2024 with where it stood on 17 Nov 2026. Of projects whose contracted date was under two years away, 64% had moved a month or more later, typically by 24 months, and 23% had left the register.
| Technology | Projects | Moved later | Typical move |
|---|---|---|---|
| Solar + storage | 35 | 91% | 24 months |
| Onshore wind | 36 | 61% | 26 months |
| Other | 33 | 61% | 31 months |
| Battery storage | 81 | 57% | 24 months |
Every project on our substation pages now shows a date risk and a likely date built from this. How we work it out.
Is your date one of them?
Tell us the project or site. We'll send you what sits ahead of it and how its date compares, free.