Benzene

Grid Delay Index

How often Great Britain's grid connection dates move, from our weekly copies of NESO's register. Updated with each new register.

25dates pushed later in November 2026 (to 17 Nov 2026)
8,428 MWof projects pushed later in November 2026 (to 17 Nov 2026)
287moves of a month or more since 2 Jun 2026
64%of projects within two years of their date moved later (two-year view)

Month by month

Each row counts connection dates that moved by a month or more between weekly copies of the register. 210 moved later and 77 earlier between 2 Jun 2026 and 17 Nov 2026; the typical later move was 19 months.

Month seenLaterEarlierMW pushed laterMonths of delay added
November 20262568,428 MW548
October 2026996233,738 MW2,722
September 20261433,110 MW269
August 20262322,792 MW391
July 20263014,875 MW672
June 20261934,243 MW377

The two-year view: near dates slip most

We compared every project waiting in our register copy of 6 Dec 2024 with where it stood on 17 Nov 2026. Of projects whose contracted date was under two years away, 64% had moved a month or more later, typically by 24 months, and 23% had left the register.

TechnologyProjectsMoved laterTypical move
Solar + storage3591%24 months
Onshore wind3661%26 months
Other3361%31 months
Battery storage8157%24 months

Every project on our substation pages now shows a date risk and a likely date built from this. How we work it out.

Is your date one of them?

Tell us the project or site. We'll send you what sits ahead of it and how its date compares, free.

Ask for a free checkSee a sample report

Journalists: you are welcome to quote these figures with credit to Benzene and a link to this page. Questions to info@benzene-group.com.